The Wastewater Improvement Project work started in 2024 and will continue over the next few years.
The improvement project consists of rehabilitating 205 existing grinder pump stations to include new pumps, piping, valves, controls, electric services, and appurtenances. Televising and cleaning of 4,400 l.f. of gravity sewer main and spot repairs and three new portable generators. The system also has 9 lift stations, two of them were rehabilitated in 2014. The remaining 7 submersible pump stations were rehabilitated over the past couple of years that included new pumps, piping, valves, controls, electric services, and appurtenances. All nine submersible station now have permanent generators installed.